GuideFlat roof rooflights

Joist spacing and the flat rooflight sizes that fit between

How flat roof joist spacing sets the rooflight sizes that sit between joists, and when a wider opening needs designed trimming instead.

A flat rooflight over a single-storey kitchen extension
A flat rooflight over a single-storey kitchen extension

Before a flat rooflight has a size, it has a grid to sit in. Underneath the deck of every timber flat roof is a row of joists running from one wall to the other, spaced at a regular interval, and those joists decide which openings are simple and which need a little engineering. Pick the rooflight first and hope it lands neatly, and you can end up cutting three joists for a window that could have sat across one. Pick it with the joist spacing in hand and the frame of the roof stays as strong as it was.

This guide is about that grid: how flat roof joists are usually laid out over an extension, garage or dormer around Basingstoke, how to work out the clear gap between them, and which sizes and orientations of skylight sit comfortably within it. It sits under our flat roof rooflight installation service, which covers the whole job from survey to finish.

Joists come before the catalogue

Rooflight makers publish their products as a list of sizes, usually quoted as the internal kerb dimension: the hole in the roof deck the unit is built to cover. It is tempting to start there and choose the size that looks right in the room below. The trouble is that a flat roof deck is not a blank sheet. It is boarding laid over parallel joists, and any opening in the deck is also an opening in the joist pattern.

If the opening falls between two joists, nothing structural is cut. If it is wider than the gap, one or more joists have to stop short of the opening, and the load they carried has to be passed sideways to the joists either side. That is routine carpentry when it is designed, but it is still a change to the roof, so it pays to know which case you are in before falling for a particular size.

Size the rooflight to the joists you have, then decide whether a bigger opening is worth the trimming.

Flat rooflight on an insulated upstand A section through a flat roof. Joists carry firrings, a deck, insulation and a waterproof membrane that falls towards a gutter at the edge. Around the opening an insulated timber upstand rises above the roof, the membrane is dressed up it and sealed under the rooflight frame, and the double glazed rooflight sits on top with a slight fall so rain runs off the glass. Inside, plasterboard lines the reveal of the opening down to the ceiling of the room below. OutsideRoom below12345678

Flat rooflight on an insulated upstand

  1. Double glazed rooflight, set to a slight fall so rain runs off the glass
  2. Upstand (kerb): a timber kerb with insulation on its outer face
  3. Membrane dressed up the upstand and over the top, sealed under the rooflight frame
  4. Waterproof membrane covering the roof, falling towards the gutter outlet
  5. Insulation laid over the deck, keeping the structure warm
  6. Roof deck on tapered firrings, which create the fall
  7. Joists, trimmed around the opening with trimmer joists
  8. Plasterboard reveal lining the opening, meeting the ceiling below

How flat roof joists are laid out

On a single storey extension the joists normally span the shorter distance across the roof, from a timber plate or joist hangers fixed to the house wall out to the far wall of the extension. On a detached or integral garage they run between the two side walls or front to back, whichever is shorter. A flat roof dormer usually has joists running from the front face of the dormer back towards the ridge side.

The standard spacings in UK timber construction are 400mm and 600mm centres, measured from the middle of one joist to the middle of the next. Closer centres are common where the ceiling below is plasterboard fixed straight to the joists, and on older roofs you will also meet spacings that were set out by eye rather than by tape. Joist depth is chosen from the span, so a wide extension has deeper joists than a narrow garage, but the spacing is what matters for a rooflight's width.

Newer extensions may use engineered I-joists instead of solid timber: a slim web of board between two timber flanges. They carry load well, but they cannot be notched or trimmed the way solid joists can, and any opening follows the joist manufacturer's own details. That is worth knowing early, because it can change which openings are practical.

Timber flat roof joists at even centres over a single storey kitchen extension
Joists over an extension roof, spaced evenly with the deck still to go on

Working out the clear gap

The number that matters is not the centres but the clear gap: the space between the faces of two neighbouring joists. Take the centres and subtract one joist thickness. Modern regularised joists are 47mm thick, and older sawn timber is often around 50mm, so the gaps come out as below. The survey measures the real figure, because a joist set a little off line changes it.

Clear gap between joists at standard centres
Joist centresJoist thicknessClear gap between faces
400mm47mm regularised353mm
400mm50mm sawn350mm
600mm47mm regularised553mm
600mm50mm sawn550mm

An opening that fits inside those figures, with a little allowance for the timber lining of the reveal, drops between two joists without cutting either. Anything wider crosses at least one joist. A gap of about 350mm gives a narrow slot of daylight rather than a window, so on a roof at 400mm centres a trimmed opening is the usual route to a useful size. At 600mm centres the single bay is wider and a modest square unit can sometimes sit within it untouched.

What each opening width asks of the roof

Think of the opening in bays. One bay is the space between two joists. Every extra bay the opening spans means one more joist stopped short, and the structure around it grows a little to match.

Opening width against the joist pattern
OpeningJoists cutWhat the frame needs
Narrower than one clear gapNoneShort noggins across the bay at each end of the opening to carry the deck and kerb
Spans two baysOneTrimmers across the ends of the opening, carried by doubled joists either side
Spans three bays or moreTwo or moreHeavier trimming checked by calculation, sometimes a structural engineer's input
Long rectangle laid along the joistsNone or oneLong side runs parallel to the joists, so a long opening stays narrow across them

None of these is wrong. A kitchen that needs real daylight may well be worth a two bay opening. The table just shows where the extra work sits, so the choice is made knowing the cost of each step up in size rather than finding out once the deck is open.

Turn the rectangle before you widen it

The simplest way to gain area without cutting more joists is to change the shape. A rectangular flat rooflight laid with its long side running the same way as the joists can be long and still narrow across the grid. Over a galley kitchen or a long hallway extension that often suits the room better anyway, because the strip of light follows the worktop or the walkway.

So a long, slim unit set along the joists may disturb the roof less than a square of similar glass area set across them. Two separate rooflights, each sitting within its own bay or pair of bays, are another way to spread light without one large trimmed hole; whether two units can share a roof neatly is covered in can two flat rooflights sit side by side.

The one thing to watch is which way the joists actually run. It is usually the short span, but not always, and a roof that was altered or extended in stages can change direction partway across. That is one of the first things confirmed on site.

What a designed opening looks like

Where the opening has to cross joists, the work follows a set order. Nothing is cut until the new timbers are ready to take the load.

  1. Locate and measure. The survey finds the joist line, direction, depth and spacing, plus anything running through the bays such as cables, extractor ducting or ceiling light boxes.
  2. Set the opening on the grid. The rooflight is placed so its edges land as close as practical to existing joists, keeping the number of cut joists to the minimum.
  3. Check the sizes. Trimming and trimmer sizes are confirmed against the span and load, and for larger openings or I-joists the relevant design details are followed.
  4. Double up and trim. The joists either side of the opening are doubled, trimmers are fixed across the ends in hangers, and only then is the joist between them cut back.
  5. Deck, kerb and covering. The deck is closed up to the new frame, the kerb or upstand goes on, and the roof covering is dressed up and around it.

Done this way the roof around the rooflight is stiffer than the plain joists alongside it, not weaker. If that worry is what is holding you back, will a flat rooflight weaken my roof answers it directly.

Where along the span the opening sits

Width is only half of it. Position along the joist span matters too. An opening near the middle of the span sits where the joists are working hardest, while one close to a supporting wall puts the trimming near a point of support. Near the house wall, though, the opening may clash with the joist hangers or wall plate, and with the flashing where the flat roof meets the house.

The room below has a say as well. A rooflight over the kitchen island, over a dining table or centred on a doorway reads well from inside, and moving it one bay left or right to suit the joists is rarely noticed once it is in. The fall of the roof matters too: water should run past the kerb, not towards it, which is explained in drainage falls around a flat rooflight.

The rule: keep the opening clear of the wall plate and hangers, and land its edges on existing joists wherever the room allows. The exception: when the light has to be in one exact place, such as over an island, the joists are trimmed to suit the room and the frame is designed around that choice.

Firrings, deck and the kerb on top

On a timber flat roof the fall is often created by tapered firring pieces nailed along the top of each joist, with the deck laid over them. The firrings run the same way as the joists, so the grid you measure from below still governs the opening from above. The deck is then cut to the same line as the trimmed frame.

On any flat roof rooflight fitting, the kerb sits on that deck and lifts the glass above the roof surface. Whether it is built in timber on site or supplied as a factory unit changes the finished height and the insulation detail, not the joist maths; the comparison is in timber upstand or factory kerb, and does a flat rooflight need a kerb gives the short answer. Either way, the internal kerb size is what lines up with the opening in the joists.

New extensions, older garages and dormers

The joist question looks a little different depending on the building. A single storey extension still under construction is the easy case: the rooflight size is fixed before the roof goes on, and the joists are set out around the opening from the start. On a finished roof the opening is formed in place, and the condition of the deck and covering matters as much as the spacing, which is why adding a flat rooflight to an existing flat roof has its own guide.

Flat roofed garages and link extensions on the 1960s and 1970s estates in Popley, Oakridge and Brighton Hill are usually solid timber joists under felt, and the timber is worth looking at closely before any opening is set out. Newer extensions in Beggarwood or Hatch Warren may use I-joists, where the opening follows the manufacturer's rules. A flat roof dormer on a loft conversion is often the tightest of the three, with shallow joists and limited room between the dormer face and the main roof.

On a pitched trussed roof the same thinking applies, with trusses rather than joists: roof windows are chosen to fit between them at 600mm centres. That side of the house is covered by our roof window installation service.

How large can a single opening go?

Bigger openings are possible, and a big single pane over a kitchen extension can be striking. The practical limits come from the glass unit, the kerb and the frame of the roof all together, not from the joist spacing alone. Each extra bay adds trimming, and past a certain point the opening wants a calculated design. What is the largest single pane flat rooflight looks at the glass side of that question.

For a room that needs a lot of daylight, it is worth weighing one large trimmed opening against a long unit along the joists or two units in neighbouring bays. The glass area can be similar, and the roof work can be quite different.

A flat rooflight on a single-storey rear extension
Figure 2 A flat rooflight on a single-storey rear extension

Building Control, and measuring your roof

A new opening in a flat roof is structural work and changes the thermal envelope, so it is notifiable under the Building Regulations. The details are in do flat rooflights need Building Regulations, and where the work is notifiable, Everlight makes that notification as part of the job.

You can often find the joists yourself from the room below: screw heads in the ceiling line up along them, and a stud finder confirms the spacing. That tells you the direction and the centres, which is enough to start thinking about shape and position. The survey then checks depth, span, timber type and what runs through the bays, and the quote follows it. Workmanship is covered by a 10-year guarantee (not insurance backed).

If you have a flat roof over a kitchen, garage or dormer and want a skylight that suits its joists, book a roof survey and the opening can be set out on your actual roof. For pitched roofs and other types, the wider picture of rooflight installation in Basingstoke starts on the homepage.

Free roof survey

Tell us about your roof

  • Survey before any quote
  • No obligation
  • Plain-English advice

Say what you have in mind and where. We survey the roof before we quote, then tell you plainly what fits.

Prefer to talk? 01256 213206

Request my survey