The honest answer to "how long" depends less on the window than on the roof and the room it goes into. On our roof window installation page the whole job is laid out from survey to finish; this answer pulls out just the timing, so you can plan a loft clearance, a day off work or a decorator around it.
It helps to split the time into three parts: the wait before anyone arrives, the hours on the roof, and the finishing inside afterwards. Only the middle part is the fitting itself, and it is usually the shortest.
What happens on the fitting day
For a window between two trusses on a concrete tiled estate roof, the working day follows a familiar pattern, and the roof is only open for part of it.
- Protect and prepare. Dust sheets go down along the route to the loft, and the opening is marked from inside against the trusses so it lands where it was agreed at survey.
- Open the roof. Tiles or slates come off around the position, the felt or membrane is cut back and the battens are trimmed to form the aperture.
- Frame and set. The window frame is fixed to the timbers at the correct height, checked for square and level, and the sash goes in.
- Weatherproof. The underfelt collar and the flashing kit for your covering are fitted, and the tiles are cut and relaid around them. From here the roof is closed.
- Tidy. Offcuts, old battens and dust leave with us, and the window is shown to you working before we go.
Weather matters for the open part of that sequence, so the day is planned around a dry forecast. If you are wondering about the colder months, our answer on whether roof windows can be fitted in winter explains how that is handled.
Sizing a roof window to the truss bays
- Fink trussed rafter, factory made and designed to work as one whole frame
- W-shaped webs, joined at every node by pressed metal nail plates
- Tile covering on battens over the underlay
- Roof window set in the slope, fitted between trusses so the frame is untouched
- Narrow roof window sitting in the bay between two trusses
- Trusses at even 600mm centres along the roof
- No truss cut: the trusses either side of the window stay whole
- A wider window crosses a truss, so the cut needs designed trimming from an engineer or the truss maker
Jobs that take longer, and why
The table sets out the common variations and what each one adds to the programme. It describes the reason, not a promise of hours; your quote gives the timing for your roof.
| Situation | What it adds | Why |
|---|---|---|
| Window between the trusses | Nothing beyond the normal fitting day | The trusses stay whole and only battens and covering are opened |
| Wider window needing trimming | Design time before the job, and more work inside the roof on the day | Trimmers must be built to the design before any truss member is cut |
| Two windows side by side | A longer fitting, often still one visit | Two apertures, two flashing kits, and matched heights |
| High or awkward roof | Scaffold erected before and struck after | Safe access comes first on a tall elevation or over a conservatory |
| Clay tile or natural slate | Extra care on the roof | Old tiles and slates are lifted and reused rather than broken |
| Finished room below | A separate finishing stage | Linings, plaster and paint need drying time between coats |
Designed trimming is the biggest single change to the timetable, because the engineering sits in front of the fitting. How that design is produced, and when a wider skylight genuinely needs it, is covered in our guide to when a wider roof window needs designed trimming.
Access decides a surprising amount
On a two storey semi in Brighton Hill or Chineham, the rear slope can usually be worked from ladders and roof ladders, and nothing needs to go up in advance. A three storey townhouse, a roof above a conservatory or a steep front slope onto a pavement is a different case: scaffold goes up first and comes down after, and that belongs in the programme even though no one touches the window on those days.
Sometimes the whole job can be done from the loft side, which keeps things simpler. Whether yours is one of those is answered in can a roof window be fitted from inside?
Finishing inside the room
A new rooflight is weathertight when the roofers leave, but the room below may not look finished. In an unconverted loft there is nothing more to do. In a bedroom, a landing or a converted loft, the opening needs insulating, lining and plastering, and plaster has to dry before it is painted. That is where calendar days appear that have little to do with the roof.
Plan for this: the window can be in and sealed long before the reveal is ready to decorate. If you want the room back in use quickly, ask for the linings to be part of the same visit. The exception is fresh plaster, which simply needs time to dry.
The options for the inside finish, from factory lining kits to plastered reveals splayed for more light, are in our guide to roof window linings and reveals.
Paperwork around the dates
Adding a roof window on a house normally involves Building Regulations, and a wider opening that alters the structure certainly does. That shapes timing in two ways: notice goes in before the work starts, and an inspection may need to fall while the trimming is still visible. We deal with the notification and fit the dates around it. The detail of what applies is in do roof windows need Building Regulations approval?
Planning is a separate matter, and only comes into the timeline in some cases, such as a front slope in a conservation area like Old Basing. If it applies, it sits well before any fitting date.
Infographic
How a rooflight job runs, from survey to guarantee
Roof survey
We look at the structure, the covering and the room below before anything is priced.
Specification
A size, type and position that fits your roof, and whether the work is notifiable.
Paperwork
Building Control notified where the work needs it, and planning checked where it applies.
Installation
Opening formed, frame fixed, flashed or dressed in, then lined and finished inside.
Sign-off and guarantee
Completion paperwork where needed and a 10-year workmanship guarantee.
How to keep your job short
Most of the delay on the day comes from surprises, and the survey is there to remove them. Before quoting, we check the truss spacing where you want the skylight, the pitch, the covering and the access, so the right window, flashing and equipment arrive together. A clear loft floor under the opening and a parking space near the house help too.
Your finished window carries a 10-year workmanship guarantee, not insurance backed. To get a timing that belongs to your roof rather than a general one, ask us to survey it and the quote will set out each stage.