That order barely changes from one house to the next, but the choices made at each stage do. A Hatch Warren semi with trusses at regular spacing, a Victorian slate roof in Reading and a 1970s flat-roofed kitchen in Popley each set different limits on where the opening can go and how wide it can be. Our work on skylight and rooflight installation across Basingstoke follows the sequence below, and the notes under each stage explain what decides it on your roof.
Before anything is cut
The installation really starts at the survey. We measure the rafter or truss spacing where you want the light, check the pitch against the window you have in mind, note the covering (concrete tile, clay tile, slate or a flat roof membrane) and look at what sits in the loft near the opening: tanks, purlins, bracing, cables. From that we confirm a window size, a flashing type and whether the timbers can stay whole. The full list of what gets checked, and why, lives in our guide on what happens at a rooflight survey.
Two paperwork points are settled here as well. Where the work is notifiable, the Building Control notification is lodged by us, so nobody is left chasing a certificate afterwards. And if the house sits in a conservation area or the window would face a road, the planning position is looked at before a date is booked, not after.
Sizing a roof window to the truss bays
- Fink trussed rafter, factory made and designed to work as one whole frame
- W-shaped webs, joined at every node by pressed metal nail plates
- Tile covering on battens over the underlay
- Roof window set in the slope, fitted between trusses so the frame is untouched
- Narrow roof window sitting in the bay between two trusses
- Trusses at even 600mm centres along the roof
- No truss cut: the trusses either side of the window stay whole
- A wider window crosses a truss, so the cut needs designed trimming from an engineer or the truss maker
The installation, stage by stage
On a pitched roof with a new roof window going in, the work on the day runs like this.
- Protect and access. Dust sheets go down inside along the route and under the opening. Outside, a roof ladder, a tower or scaffold is set up depending on the height and what lies below.
- Mark out. The position is set out from inside and outside so the frame lands between two rafters or trusses and lines up with the tile courses.
- Strip the covering. Tiles or slates are lifted over the marked area and stacked for reuse, the battens are cut back and the underlay is opened.
- Frame the opening. Timber noggins go in above and below to form a square hole. Where a wider window was agreed at survey, the designed trimming is built at this point, before any truss member is cut.
- Fix the frame. The window frame is screwed to the rafters on its brackets, checked for level and square, and the sash is tried to make sure it opens freely.
- Weatherproof. An underlay collar is fitted round the frame, then the flashing kit made for that covering profile is laid and dressed so water runs over and around the window.
- Relay the covering. Battens are reinstated round the flashing and the tiles or slates go back, cut where they meet the frame.
- Line the inside. The ceiling or sloping plasterboard is cut back to the frame, insulation is packed round it, and a lining panel or plasterboard reveal closes the gap ready for decorating.
How the order changes on a flat roof
A flat rooflight on an extension or garage follows the same logic with different parts. The hole is cut through the deck between the joists and framed, then a timber or factory upstand is fixed round it so the glazing sits above the water line. The roof covering, whether felt, single ply or liquid applied, is turned up the upstand and finished to it, and the rooflight is bolted down on top. Inside, the reveal is boarded and finished much as it is under a pitched roof.
When an old plastic dome is coming off rather than a new hole being made, the existing kerb is checked first, since a modern unit may need a new upstand to reach the height and fall it wants. That replacement path is covered in our guide to replacing the plastic domes on 1970s and 1980s flat roofs.
The rule: the covering is always relaid to the new frame with the flashing made for it, never with sealant alone. The exception is a flat roof, where the membrane itself is dressed up the upstand instead of a separate flashing kit.
What decides each step on your roof
Most of the variation comes from four things found at survey, and they are worth knowing before you picture the job.
| What the survey finds | Stage it affects | What changes |
|---|---|---|
| Trusses at 600mm centres | Framing the opening | A width that fits between trusses keeps them whole; wider needs designed trimming first |
| Cut rafters in an older house | Marking out and framing | Spacing is measured on the day and rafters can be trimmed by conventional carpentry |
| Slate or plain clay tile | Flashing and relaying | A flatter flashing profile and more careful cutting round the frame |
| A converted or finished ceiling | Lining the inside | More plasterboard to cut back and make good before decorating |
After the frame is in
Once the window is weathertight the outside part of the job is complete, even if the inside still needs finishing. The reveal can be skimmed or taped and filled, then painted once dry; that last coat is usually left to you or your decorator. What the room looks like once the plasterboard has been cut and closed again is explained in what happens to the ceiling when a skylight is fitted.
Where Building Control inspects, the visit follows completion and the certificate comes through the notification we lodged. The work is covered by a 10-year workmanship guarantee from us; it is a promise about the fitting and is not insurance backed.
Infographic
How a rooflight job runs, from survey to guarantee
Roof survey
We look at the structure, the covering and the room below before anything is priced.
Specification
A size, type and position that fits your roof, and whether the work is notifiable.
Paperwork
Building Control notified where the work needs it, and planning checked where it applies.
Installation
Opening formed, frame fixed, flashed or dressed in, then lined and finished inside.
Sign-off and guarantee
Completion paperwork where needed and a 10-year workmanship guarantee.
Access, time and mess
Three practical points sit alongside the sequence. Whether a tower or full scaffold is needed depends on the height of the eaves, the pitch and what sits under the roof, such as a conservatory or a sloping garden, and our answer on whether fitting a skylight needs scaffolding walks through it. How long each version takes is set out in how long it takes to replace a skylight. Cutting plasterboard is the dusty part of the job, and the sheeting and clean-down at the start and end of the day are there for that reason.
If you would like the stages mapped onto your own roof, with the window size, flashing and access worked out before any price is written, arrange a survey and we will walk the loft and the roof with you.