Doubling up is the carpenter's answer to a missing piece of roof. Take a length out of one rafter and its share of the tiles, battens and wind load has to go somewhere, so the timbers beside the gap are thickened to carry it. Whether your roof window needs that depends on two measurements: the width of the window and the space between your timbers. Our VELUX window installation service starts from those two numbers, because they decide whether the job is a simple fit or a structural one.
When no rafter is touched
VELUX frames come in a range of widths, and the narrower ones are made to sit inside the bay between timbers at standard spacing. Where the frame fits the bay, the installer opens the tiles and battens, fixes the window to the rafters on each side with its brackets, and fits a trimmer only where the head and sill need something solid to finish against. The rafters themselves stay full length and carry exactly what they carried before, so there is nothing to double.
That is why the width choice matters so much on an estate roof. A taller window in a narrow width can bring in plenty of daylight without asking the structure for anything. The widths that suit 600mm trusses are set out in our guide to VELUX sizes that fit between trusses, and the full list of codes is in what are the standard VELUX window sizes?
Sizing a roof window to the truss bays
- Fink trussed rafter, factory made and designed to work as one whole frame
- W-shaped webs, joined at every node by pressed metal nail plates
- Tile covering on battens over the underlay
- Roof window set in the slope, fitted between trusses so the frame is untouched
- Narrow roof window sitting in the bay between two trusses
- Trusses at even 600mm centres along the roof
- No truss cut: the trusses either side of the window stay whole
- A wider window crosses a truss, so the cut needs designed trimming from an engineer or the truss maker
When a rafter is cut and why the neighbours get doubled
If you pick a window wider than the bay, one rafter (sometimes more) has to be shortened. The cut rafter now stops at the top and bottom of the opening instead of running from wall plate to ridge. Horizontal trimmers are fixed across the head and the sill to catch its ends, and those trimmers hand the load sideways to the rafters on each side. Those side rafters are now carrying their own share plus part of the one that was cut, so they are doubled: a second timber of matching depth is fixed alongside, bolted or nailed to a set pattern, and runs the full length of the slope.
The rule: cut one rafter, double the two beside it and trim top and bottom. The exception: where the timbers are unusually deep, the span is short or an engineer has calculated something different, the specification may change, so the survey and any design decide the detail rather than a rule of thumb.
Cut rafters and trussed rafters need different answers
The doubling described above belongs to the traditional cut rafter roof, built on site from loose timbers, which is what you find in the older cottages of Old Basing, Overton or Kingsclere. On those roofs rafter spacing is not fixed, so the survey measures it bay by bay before any window width is chosen.
A trussed roof, the kind on the Popley, Brighton Hill or Chineham estates, is a set of factory-made frames joined with metal plates and braced to act together. There, the equivalent step is a doubled or tripled truss either side of the gap, but it is never improvised from the cut rafter pattern. The truss designer or a structural engineer specifies it for that roof.
| Situation | Cut rafter roof | Trussed rafter roof |
|---|---|---|
| Window fits inside one bay | No doubling; trimmers at head and sill if needed | No doubling; every truss stays whole |
| One timber must be shortened | Rafters either side doubled, trimmers top and bottom | Designed trimming, often doubled trusses, to a written specification |
| Two windows side by side | One rafter left between them, or a trimmed opening | A whole truss left between them where the spacing allows |
| Who decides the detail | The survey, with an engineer where the roof is unusual | The truss designer or a structural engineer |
How to avoid doubling altogether
If the room needs more light than one narrow window gives, two windows in neighbouring bays usually beat one wide window that forces a cut. Each sits between its own pair of timbers, the rafter or truss between them stays whole, and the pair can be matched for a tidy look inside. Our answer on fitting VELUX windows in a row covers how the flashing combines, and choosing the right VELUX size walks through matching window height to the room.
A tall narrow roof window can also give as much glass as a squat wide one. In a loft room, height brings the view down to eye level, so it is often the better choice for the room as well as for the roof.
What the doubling job involves
Where a cut really is the right call, the order of work keeps the roof supported throughout.
- Measure. Timber depth, spacing, pitch and anything bearing on the roof near the opening are recorded at survey.
- Specify. The timber sizes, fixings and, on a trussed roof, the written trimming design are settled before a saw comes out.
- Notify. Changing roof structure is notifiable, and the Building Control notification is part of the job we carry out on your behalf.
- Double first. The new timbers go in alongside the neighbours and the trimmers are fixed before the rafter is cut, so the load always has a path.
- Fit. The VELUX frame, flashing and lining go in, then the inside is made good.
That structural work falls under the 10-year workmanship guarantee along with the window, which is a guarantee from us and is not insurance backed.
New homes and loft conversions
On a newer house still inside a housebuilder warranty, read the warranty terms before any roof timber is altered; a window that fits between the trusses sidesteps the issue entirely. See can a VELUX go into a new build roof? for that situation. In a loft that has already been converted, the conversion may have added steel or new rafters, so what is behind the plasterboard is checked before a skylight or rooflight width is agreed.
If you want to know whether your idea needs doubled timbers at all, ask us to measure the roof and we will show you the answer on your own rafters.