So the honest answer comes in two halves: the day the glass goes on, and everything that makes that day possible. Our roof lantern installation work is planned around that split, and the survey is where we find out which half will take the time on your extension.
Below is what each stage involves, what stretches it, and how to keep the kitchen or family room usable while the roof is open.
The day the lantern goes on
Where a new extension has been built with a correctly sized, level kerb and the flat roof covering already turned up it, the lantern arrives as a frame and a set of glazed units. The frame is set onto the kerb and fixed, the ridge and hips go together, the sealed units are bedded into the glazing bars and the capping clips over them. Then the roof membrane or GRP is finished against the kerb so rain runs past it and off the fall.
That is a morning of lifting and fixing and an afternoon of glazing and finishing for a standard sized unit. A large lantern, or one with heavy triple glazed units, may need a second pair of hands or lifting gear, and the plan for getting it up there matters as much as the fitting. Our guide to getting a roof lantern onto the roof covers side access, terraced houses and when the glass has to come through the house.

How a roof lantern sits on a flat roof
- Ridge, where the glazing bars meet at the top
- Hip bar, closing each sloped end of the lantern
- Glazing bar, holding the edges of the glass
- Glass panel, sealed double or triple glazed units
- Eaves or perimeter frame, which the whole lantern stands on
- Insulated kerb (upstand), raising the lantern clear of the roof
- Flat roof covering, dressed up the kerb and under the frame
- Plastered reveal, lining the lantern well into the room below
Work that happens before that day
On an estate house around Basingstoke, the lantern often goes into an extension that already exists: a single storey kitchen on the back of a Chineham semi, or a converted garage roof on a Brighton Hill link house. There the opening has to be made first, and that takes longer than the fitting.
- Survey. We measure the flat roof, find which way the joists run, check the covering and the fall, and look at access from the road to the back of the house.
- Ordering. The lantern is made to the kerb size, so the frame and glass are ordered once the opening is fixed. Manufacturing lead time sits here, before anyone works on your roof.
- Opening and trimming. The ceiling below is protected, the covering and deck are cut back, and joists are trimmed round the opening to the agreed design.
- Kerb. A timber kerb is built to the lantern size, insulated and set level, tall enough to keep the frame clear of water on the roof.
- Weatherproofing. The covering is taken up the kerb so the room is dry even before the lantern arrives.
- Lantern day. Frame, glazing, capping and final dressing.
- Inside finish. The reveals are lined, plastered or boarded, ready for your decorator.
How tall the kerb should be and how the roof has to fall away from it is set out in our guide on kerb height and falls. It is worth reading before the builder lays a new flat roof, because a kerb built right first time saves a day later.
What stretches the timeline
Most of the variation comes from the roof, not from the lantern. The table sets out the common causes and where in the job they add time.
| Factor | Why it adds time | When it shows up |
|---|---|---|
| Joists running the wrong way | More joists are cut, so more trimming and possibly an engineer's design | Before and during the opening |
| Tired flat roof covering | The covering may need renewing so it can be dressed to a new kerb properly | Before lantern day |
| Difficult access | Glass carried through the house or lifted over a neighbour's side needs planning and extra hands | On lantern day |
| Rain or high wind | Membranes and sealants need dry surfaces, and large glass cannot be lifted safely in wind | Any open-roof stage |
| Building Control inspection | Structural work is checked at set points, so a visit is booked into the sequence | After trimming, and at completion |
Structure, sign-off and the weather
If joists are cut to form the opening, the work is notifiable, and we make that notification on your behalf so it runs alongside the build. Whether your job needs an engineer's calculation first is answered in does a roof lantern need a structural engineer?, and the wider regulations question sits in do roof lanterns need Building Regulations approval?
Weather is the other variable. A kerb that is sealed and weathered can sit through a wet week without trouble, which is why we close the roof before the lantern day rather than leaving it open to a forecast. Our answer on whether a roof lantern can be fitted in winter explains how the shorter days and colder surfaces are planned for.
The rule: the roof is not left open overnight. The exception: if a stage cannot be finished before dark, the opening is sheeted and sealed and the stage picks up the next morning.
Living with the work in progress
Because a lantern usually goes over a kitchen or open-plan family room, the practical question is how long the room is out of use. On a new build extension the room is not finished yet, so the lantern simply slots into the builder's programme. On an existing kitchen, the noisy, dusty part is the opening and trimming, when the room below is sheeted and the worktops protected. Once the kerb is weathered, the kitchen can usually be used again while the lantern waits to be delivered. Only the ceiling reveal is left unfinished until the rooflight or skylight, whichever name you know it by, is in place and the lining goes on.
We clear up at the end of each day so you are not living on a building site any longer than the work needs.
Infographic
How a rooflight job runs, from survey to guarantee
Roof survey
We look at the structure, the covering and the room below before anything is priced.
Specification
A size, type and position that fits your roof, and whether the work is notifiable.
Paperwork
Building Control notified where the work needs it, and planning checked where it applies.
Installation
Opening formed, frame fixed, flashed or dressed in, then lined and finished inside.
Sign-off and guarantee
Completion paperwork where needed and a 10-year workmanship guarantee.
Getting a firm timeline for your roof
The only reliable answer for your extension comes from seeing it. At the survey we tell you whether the kerb is ready or has to be built, whether the joists help or hinder, and what access looks like, then set out each stage and its order in your written quote. The finished work carries a 10-year workmanship guarantee (not insurance backed). If you would like the lantern day pinned to a date, arrange a roof survey and the stages can be planned around your household.