How a rooflight replacement day runs, start to finish

What happens on a rooflight replacement day, from protecting the house and lifting the old frame out to flashing, lining and the handover.

An old rooflight on a flat roof due for replacement
An old rooflight on a flat roof due for replacement

The day a rooflight is swapped is the shortest part of the whole job, and also the one people picture least clearly. Who turns up first, when the old unit comes out, how long the roof sits open, what happens if the timber around the opening is not what anyone expected: these are fair things to want to know before you book time off work. This guide walks through a replacement day in the order it actually unfolds, from the van pulling up to the moment you are shown how the new skylight opens and closes.

It assumes the planning has already been done. The size, the product and the route onto the roof were settled at the survey, so nothing on the day is a guess. What follows is the sequence, the decisions that still sit with you, and the few points where the plan can change.

The evening before: three things worth doing

You do not need to prepare much, but a little clearing makes the morning quicker. The fitters will bring dust sheets and protection; what they cannot do is move a wardrobe full of clothes or unplug a home office without asking.

  • Clear a path. The route from the front door to the room below the rooflight needs to be free of shoes, bikes and anything fragile on the stairs. A frame and its glazing are awkward to carry round a tight landing.
  • Empty the space under the window. Roughly the floor area of a single bed beneath the opening is enough. Beds and desks that cannot move will be sheeted.
  • Think about parking and the side of the house. If access or a tower is going up at the side or rear, an open side gate and a clear drive save time at the start.

If the rooflight is over a flat roof extension reached through a garden, it helps to know where the nearest outside tap and power point are. Nothing else needs doing; the rest is the fitters' job.

Sizing a roof window to the truss bays On the left, a section through a pitched roof built from Fink trussed rafters, with W-shaped webs joined by nail plates, tiles on battens, and a roof window set in the slope. On the right, the same slope seen square-on: trusses at even 600mm centres with a narrow roof window sitting in the bay between two of them, so no truss is cut. A wider window outline, drawn dashed, crosses a truss and would need designed trimming. Section600mm centresSeen square-on12345678

Sizing a roof window to the truss bays

  1. Fink trussed rafter, factory made and designed to work as one whole frame
  2. W-shaped webs, joined at every node by pressed metal nail plates
  3. Tile covering on battens over the underlay
  4. Roof window set in the slope, fitted between trusses so the frame is untouched
  5. Narrow roof window sitting in the bay between two trusses
  6. Trusses at even 600mm centres along the roof
  7. No truss cut: the trusses either side of the window stay whole
  8. A wider window crosses a truss, so the cut needs designed trimming from an engineer or the truss maker

Arrival and the walk round

The first thing that happens is not tools. It is a short walk round with you: the room, the old unit, the way onto the roof. The fitter checks the survey notes against what is in front of them, confirms the new frame on the van is the one that was agreed, and points out anything that has changed since the survey, such as fresh cracking in the plaster around the old lining or a tile that has slipped in the weather.

This is also when you mention the things only you know. A fire alarm that trips on dust, a dog that needs to stay in the kitchen, a neighbour whose drive is shared. None of it is fussy, and it shapes how the day is set up.

The rule: nothing is removed until the replacement unit has been checked against the opening size on the survey sheet. The exception is when the old frame has to come out to reveal the true opening, which the survey flags in advance so it is never a surprise on the day.

Protecting the house before the roof is opened

Once the plan is agreed, the inside goes under cover. Floors from the door to the window are sheeted, the room below the opening is screened, and anything electrical near the work area is protected. The detail of how that is done, and how the room is left afterwards, has its own guide: dust, protection and the room afterwards. The short version is that the dirty part of the job is contained before a single fixing is undone.

Outside, access goes up. On a pitched roof that can be roof ladders, a tower or scaffold, depending on the height, the slope and what sits underneath; the choice was made at the survey and is explained in whether fitting a skylight needs scaffolding. On a single-storey flat roof the route is often a ladder and a protected edge. Access is checked before anyone steps on the roof covering.

Loft landing with floor sheeted and the old roof window lining exposed ahead of a replacement
The room is covered and screened before the old frame is touched

Taking the old rooflight out

With the house protected, the old unit comes out in the reverse of the order it went in. On a pitched roof window, the sash is lifted away first, which makes the frame lighter and safer to handle. Then the external cladding and flashing are unclipped or cut free, the tiles or slates immediately around the frame are lifted and stacked, and the frame itself is unscrewed from its brackets and lifted clear.

On a flat roof the sequence is different. An old plastic dome or fixed unit is unscrewed from its kerb, and the question becomes whether the kerb stays. If the survey found it sound and the right height, it stays and the new unit sits on it. If not, it comes out too, and the roof covering around it is cut back ready for a new upstand. The misted and failed rooflight replacement service page covers when each route applies.

Whether the job is done from inside or outside depends on the product and the roof. Some roof windows allow the frame to be changed largely from within the room; the trade-offs are set out in can a skylight be replaced from inside.

The open roof: what gets looked at

This is the moment of the day that matters most, and it is quiet. With the old frame out, the fitter can see the timbers around the opening for the first time since the house was built. They look for three things.

  1. The trimmers and rafters or trusses either side. Are they dry, straight and firmly fixed? On a trussed estate roof, are the trusses either side of the opening untouched, as they should be?
  2. The opening size. Does it match the survey measurement, and is it square? Old frames sometimes hid an opening that was cut a little out of true.
  3. The membrane and battens. Is there an underlay to lap the new collar into, and are the battens around the opening sound enough to fix to?

If everything is as expected, which a thorough survey is designed to make likely, the day carries on without pause. If something is not, you are told straight away, shown it, and given the choice before any work goes further. A soft batten is replaced as a matter of course. Anything structural is a conversation, not a decision made on your behalf.

The old frame coming out is the only time anyone sees the roof timbers bare, so it is the moment to look properly.

Fitting the new frame and flashing

The new frame goes in to the same line as the old one unless a size change was agreed. On a pitched roof, mounting brackets are fixed to the rafters or trimmers, the frame is set to height against the tiling battens so it will sit correctly with the roof covering, and it is checked for square across both diagonals. A frame that is out of square will bind when it opens, so this check is not skipped.

An insulation collar and an underfelt collar follow on current roof windows, lapped into the existing membrane so water on the underlay is led round the frame rather than into the room. Then the flashing kit goes on, matched to the covering: a profiled kit for deep tiles, a flatter kit for slate or plain tile. The question of whether the old flashing could have been reused comes up often enough to have its own answer; on a replacement day the new frame is fitted with the flashing made for it.

The tiles or slates are then laid back around the frame, cut where needed, and the sash is hung and adjusted. On a flat roof the equivalent is the new upstand or the existing kerb being prepared, the unit fixed down, and the roof covering dressed up the side of the kerb to the manufacturer's detail.

Where the time goes on a replacement day

The day has a rhythm, and it helps to know which part is which so that a quiet hour in the middle does not look like a stall. The table below gives the stages in order and what you would notice in the house during each one. There are no clock times, because the survey decides how long each stage takes on your particular roof; for a direct answer on overall duration, see how long it takes to replace a skylight.

A rooflight replacement day in order
StageWhat happensWhat you notice indoors
Walk roundSurvey notes checked against the roof and the new unitA short conversation, no noise
Protection and accessSheets and screens inside, ladders, tower or scaffold outsideCovered floors and a screened room
Old unit outSash, flashing, surrounding tiles and frame removedSome noise and a draught through the opening
Opening checkedTimbers, size, square and membrane inspectedQuiet; you may be asked to take a look
New frame and flashingFrame fixed, collars lapped, flashing fitted, tiles relaidThe opening is closed and weathertight again
Lining and finishInner lining fitted, gaps insulated, trims setWork moves inside to the ceiling
Clear up and handoverProtection lifted, waste removed, window demonstratedThe room back in use

The stretch between the old frame coming out and the new one being flashed is kept as short as the work allows, and it is planned around the weather forecast when the day is booked. A roof is not left open overnight on a straightforward replacement.

Infographic

How a rooflight job runs, from survey to guarantee

  1. Roof survey

    We look at the structure, the covering and the room below before anything is priced.

  2. Specification

    A size, type and position that fits your roof, and whether the work is notifiable.

  3. Paperwork

    Building Control notified where the work needs it, and planning checked where it applies.

  4. Installation

    Opening formed, frame fixed, flashed or dressed in, then lined and finished inside.

  5. Sign-off and guarantee

    Completion paperwork where needed and a 10-year workmanship guarantee.

Inside: the lining and the ceiling

Once the roof side is weathertight, attention turns to the room. On a like-for-like swap the old plaster reveal can sometimes stay, with a new trim covering the joint to the frame. Where the new frame sits differently, or the old reveal was cracked, a new lining is fitted: either a factory lining panel or plasterboard cut to suit. Gaps between the frame and the reveal are packed with insulation so the new unit is not let down by a cold edge.

What happens to the ceiling depends on how different the new frame is from the old one, and on the state of the finish around it. The possible outcomes, from a clean trim to a reveal that needs a plasterer's skim once it has settled, are laid out in what happens to the ceiling when a skylight is fitted. Whatever applies to your room was discussed at the survey, so the finish you see at the end of the day is the one you were told to expect.

Paperwork on the day

Replacing a rooflight is usually notifiable under the Building Regulations, because the new unit has to meet the current thermal standard. Everlight deals with that notification, and on the day it simply means the fitter records what was installed. You do not have to contact the council yourself. How the process works, and what document arrives afterwards, is covered in the guide to Building Control notification for a rooflight.

You are also left the product details for the new unit: the model, the glazing, and the care notes from the manufacturer. Keep them with the house documents. If you sell, a buyer's solicitor may ask what was fitted and when.

Handover: the last half of the last stage

Before anyone packs up, you are shown the window working. How it opens, how the ventilation flap or trickle vent works, how a blind clips in if one was ordered, and on an electric or solar unit how the remote pairs and what the rain sensor does. It is worth trying each of these yourself while the fitter is still there.

The protection comes up, the floors are checked, and the old frame and waste leave on the van. The outside is looked over from the ground and, where access allows, from the roof: tiles bedded back, no loose offcuts in the gutter, flashing dressed tight.

The workmanship on the new rooflight is guaranteed for ten years. That guarantee is Everlight's own and is not insurance backed, and the terms are handed over with the product details so there is no need to chase them later.

When the plan changes mid-day

A replacement day is predictable because the survey did the uncertain work in advance. Still, a roof can hold something the survey could not see from the loft or the ground. The honest list of what might change the plan is short.

  • Timber that is wetter or softer than expected around the old frame. Battens are replaced there and then; anything more is shown to you before a decision is made.
  • An opening that was cut for a frame size no longer made. The survey should catch this, and the product ordered takes it into account.
  • Weather that turns. The old frame is not taken out if rain is due before the new one can be weathered in. The day is moved rather than gambled.

If the plan does change, you hear it as it happens, in plain terms, with what it means for the finish and the day. Nothing is added to the work without you agreeing to it first.

A new replacement rooflight on a flat roof
Figure 3 A new replacement rooflight on a flat roof

Before you book the day

Most of what makes a replacement day calm is decided earlier. The survey confirms the opening, the access and the product, as described in what happens at a rooflight survey. The choice between the same size again and something better or larger is covered in like for like or upgrade, and that choice affects how much of the day is spent on the roof versus on the lining.

For the wider picture of replacing a tired skylight anywhere around Basingstoke, the skylight and rooflight replacement pages on the homepage bring the options together. If you already know the window needs changing and want the day planned properly, arrange a survey of your roof and the sequence above will be fitted to your house. You can also start from the Everlight homepage to see how the fit check works on estate roofs.

Free roof survey

Tell us about your roof

  • Survey before any quote
  • No obligation
  • Plain-English advice

Say what you have in mind and where. We survey the roof before we quote, then tell you plainly what fits.

Prefer to talk? 01256 213206

Request my survey